S.B. Ballard Stadium Begins Taking Shape

By Harry Minium

After nearly three months of demolition, pile driving and pouring foundation, the new S.B. Ballard Stadium has finally begun to rise out of the ground.

Construction began last summer with the installation of underground utility lines, then was halted for the 2018 football season.

Demolition of the old stadium began Nov. 19, two days after ODU played its football home finale against VMI. That game was followed by an emotional farewell ceremony to Foreman Field at S.B. Ballard Stadium.

Demolition was done in just three weeks and 670 piles were driven by Dec. 22, days ahead of schedule. S.B. Ballard Construction has been pouring the foundation for the new stadium in the two months since.

A crane recently began installing precast concrete that will form the indoor space on the ground floor of the new east and west sides of the stadium, including concessions stands, restrooms and equipment and storage rooms.

A tower that will house an elevator and stairwell for the new west side press box is now three stories high and growing.

Construction will end before the home opener of the 2019 football season.

Work began on the west side on Valentine's Day. Greg DuBois, vice president of finance and administration, calls the installation of precast and steel "one of the crucial phases of construction."

Precast concrete is used in most of the world's best stadiums. It is more durable than facilities constructed on site. It also limits vibration and allows for faster construction.

By mid-March, more cranes will be on site erecting the steel that holds up new stadium seating.

ODU is doing a $67.5 million renovation that will provide new seats on both sidelines. Both will have two levels of seats, and the west side will be topped by a new press box and also contain the $2.5 million Priority Automotive Club.

Foreman Field at S.B. Ballard Stadium had a maximum capacity of 20,118. The new stadium will seat 21,895 fans, with an all-in capacity of 22,480 if the media, ushers, ticket takers and others are included.

ODU is scheduled to meet Norfolk State on Aug. 31 in the first game in the new stadium.

Work at the stadium can be viewed on three S.B. Ballard video cameras.

Link to Ballard video cameras

Related News Stories

chemistry1

University to Begin Construction of New Chemistry Building

The $75.6 million, 4-story facility set to open in 2020 will allow ODU to graduate more STEM-H students and expand research. (More)

Fred Chao, and Wood Selig.

Women's Volleyball Program Off to a Promising Start

ODU has a smart, well-funded plan for its new program and seems to have hit a home run with coach Fred Chao. (More)

For All to See

Banksy Work on Display at Baron and Ellin Gordon Art Galleries

The famed anonymous English street artist's "Haight Street Rat" can be viewed through April 7. (More)


Site Navigation

Experience Guaranteed

Enhance your college career by gaining relevant experience with the skills and knowledge needed for your future career. Discover our experiential learning opportunities.

Academic Days

Picture yourself in the classroom, speak with professors in your major, and meet current students.

Upcoming Events

From sports games to concerts and lectures, join the ODU community at a variety of campus events.